Quantcast
Channel: Dublin City Council - Roads and Traffic
Viewing all 755 articles
Browse latest View live

Philipsburgh Avenue, Dublin 3.

$
0
0

A request has been received from Gas Networks Ireland for the temporary closure of the following road to facilitate gas works on Philipsburgh Avenue between Annadale Avenue and Foyle Road dates and times listed below:

  • Philipsburgh Avenue (from Griffith Avenue to Fairview Strand), Dublin 3 from 08.00hrs on Sunday 19th March 2017 to 06.30hrs on Monday 20th March 2017.

Traffic Management Plan

  • Pedestrian and local access will be maintained.
     

St. Patrick's Festival 2017

$
0
0

A request has been received from St. Patrick’s Festival for the temporary closure of the following roads to facilitate the St. Patricks Festival Event, during the periods listed below:

St. Patrick’s Day Parade

Location A:

  • Western Way from 18.00hrs on Thursday 16th March 2017 to 15.00hrs on Friday 17th March 2017.

Location B:

  • Mountjoy Street, Mountjoy Street Middle, Palmerstown Place, Wellington Street, St Mary’s Place North, Dominick Street Upper, Granby Row,
  • Parnell Square North, Parnell Square East, Cavendish Row, O’Connell Street Upper & Lower, O’Connell Bridge, Westmoreland Street, College
  • Green, Dame Street, Lord Edward Street, Christchurch Place,  Nicholas Street, Patrick Street, New Street South,  Clanbrassil Street Lower, Kevin
  • Street Upper, Kevin Street Lower, Cuffe Street and St Stephens Green South from 04.30hrs to 18.00hrs on Friday 17th March 2017.

Traffic Management Plan

  • Traffic on Arran Quay travelling north and east will be diverted via Church Street, Constitution Hill, North Circular Road, Portland Row and Amiens Street.
  • Traffic on North Wall Quay travelling south will be diverted via City Quay Lombard Street, Westland Row, Merrion Square North, and Mount Street Lower.
  • Traffic on North Wall Quay travelling west will be diverted via George’s Quay Beresford Place, Gardiner Street, North Circular Road, Infirmary Road, Parkgate Street.  
  • Pedestrian access will be maintained.

St. Patrick’s Festival – Custom House Quay Funfair

  • Customs House Quay (from Eden Quay to Memorial Road) from 19.00hrs on Thursday 16th March 2017 to 06.00hrs Sunday 19th March 2017.

Traffic Management Plan

  • Traffic from Eden Quay / Butt Bridge wishing to travel on Custom House Quay will be diverted via Beresford Place and Memorial Road
  • Pedestrian access will be maintained.

St. Patrick’s Festival – Merrion Square Funfair

  • Merrion Square West from 19.00hrs on Thursday 16th March 2017 to 06.00hrs on Sunday 19th March 2017.

Traffic Management Plan

  • Traffic from Clare Street / Merrion Street Lower will be diverted via Merrion Square North / Mount St Lower / Warrington Place / Herbert Place / Baggot Street Lower.
  • Traffic from Merrion Row and will be diverted via Baggot Street Lower, Fitzwilliam Street Lower, Merrion Square East and Merrion Square North.
  • Pedestrian access will be maintained.

St. Patrick’s Festival - Ceili

  • Earlsfort Terrace (from Leeson Street Lower to Hatch Street Upper) from 08.00hrs to 21.00hrs on Thursday 16th March 2017.  

Traffic Management Plan

  • Traffic on Hatch Street Upper wishing to travel to St Stephens Green will be diverted via Hatch Street Lower and Leeson Street Lower.
  • Pedestrian and local access will be maintained.

St. Patrick’s Festival – Big Day Out

  • Merrion Square South and Merrion Street Upper from 14.00hrs on Saturday 18th March 2017 to 23.00hrs on Sunday 19th March 2017.

Traffic Management Plan

  • Traffic on Merrion Square North wishing to travel on Merrion Square West to Baggot Street Lower will be diverted via Merrion Square East and Fitzwilliam Street Lower.
  • Traffic on Merrion Row wishing to travel on Merrion Street Upper & Merrion Square West to Clare Street will be diverted via Baggot Street Lower, Fitzwilliam Street Lower, Merrion Square East and Merrion Square North.
  • Pedestrian access will be maintained.

St. Patrick’s Festival – Treasure Hunt

  • Castle Street from 08.00hrs to 18.00hrs on Saturday 18th March 2017.

Traffic Management Plan

  • Traffic wishing to travel on Castle Street to Werburgh Street will be diverted via Lord Edward Street
  • Pedestrian and local access will be maintained.

St. Patrick’s Festival – 5k Road Race

  • St. Stephen’s Green South from 10.00hrs to 13.00hrs on Sunday 19th March 2017.

Traffic Management Plan

  • Traffic on Leeson Street Lower wishing to travel on St Stephens Green South to Cuffe Street & St Stephens Green West will be diverted via Earlsfort Terrace, Hatch Street Upper and Harcourt Street.
  • An Garda Siochana will operate traffic control measures on the race route.
  • Pedestrian access will be maintained.
     

Hanover Street East, Dublin 2.

$
0
0

A request has been received from Gas Networks Ireland for the temporary closure of the following road to facilitate gas connection works on the date and times listed below:

  • Hanover Street East (from Lime Street to Macken Street), Dublin 2 from 08.00hrs to 20.00hrs on Saturday 25th March 2017.

Traffic Management Plan

  • Traffic on Lime Street wishing to travel on Hanover Street East to Macken Street will be diverted via Pearse Street
  • Pedestrian and local access will be maintained.
     

Paradise Place, Dublin 1.

$
0
0

A request has been received from Bennett Construction Ltd. for the temporary closure of the following road to facilitate tower crane removal on the dates and times listed below:

  • Paradise Place (from St. Mary’s Place North to Wellington Street Lower), Dublin 1 from 00.00hrs on Saturday 25th March 2017 to 24.00hrs on Sunday 26th March 2017.

Traffic Management Plan

  • Pedestrian and local access will be maintained.

Charlemont Place, Dublin 2.

$
0
0

A request has been received from Gas Networks Ireland for the temporary closure of the following road to facilitate gas works on the dates and times listed below:

  • Charlemont Place (from Harcourt Terrace to cul de sac), Dublin 2 from 00.00hrs on Monday 27th March 2017 to 24.00hrs on Friday 31st March 2017.

Traffic Management Plan

  • Premium Cycle Route will be maintained.
  • Pedestrian and local access will be maintained.
     

Nephin Road, Dublin 7.

$
0
0

A request has been received from Actavo (Ireland) Ltd. for the temporary closure of the following road to facilitate road reconstruction on the dates and times listed below:

  • Nephin Road (from Navan Road to Blackhorse Avenue), Dublin 7 from Wednesday 29th March 2017 to 24.00hrs on Friday 19th May 2017.

Traffic Management Plan

  • Inbound traffic on Navan Road wishing to travel on Nephin Road to Blackhorse Avenue will be diverted via Baggot Road.
  • Outbound traffic on Navan Road wishing to travel on Nephin Road to Blackhorse Avenue will be diverted via Skreen Road.
  • Traffic on Blackhorse Avenue wishing to travel on Nephin Road to Navan Road will be diverted via Screen Road.
  • Pedestrian and local access will be maintained.

Fleet Street, Dublin 2.

$
0
0

Sisk Steconfer Joint Venture intends to close the following road to facilitate Luas Cross City works on the dates and times listed below:

  • Fleet Street (from Westmoreland Street to D’Olier Street), Dublin 2 from 00.00hrs on Friday 24th March 2017 to 24.00hrs on Monday 27th March 2017.       

Traffic Management Plan

  • Traffic on Westmoreland Street wishing to travel on Fleet Street to Townsend Street and College Street will be diverted via D’Olier Street.
  • Pedestrian and local access will be maintained.
     

Henry Street

$
0
0

Sisk Steconfer Joint Venture intends to close the following road to facilitate Luas Cross City works on the dates and times listed below:

  • Henry Street (from O’Connell Street to Liffey Street Upper), Dublin 1 from 00.00hrs on Monday 20th March 2017 to 24.00hrs on Sunday 30th April 2017.

Traffic Management Plan

  • Pedestrian and local access will be maintained.
     

Station Road, Dublin 5.

$
0
0

A request has been received from Irish Rail for the temporary closure of the following road to facilitate bridge renewal works on the dates and times listed below:

  • Station Road (Howth Road to Springdale Road), Raheny, Dublin 5 from 22.00hrs on Friday 14th April 2017 to 18.00hrs on Saturday 15th April 2017. 

Traffic Management Plan

  • Outbound traffic on Howth Road wishing to travel on Raheny Road will be diverted via Howth Road and Kilbarrack Road.
  • Inbound traffic on Howth Road wishing to travel on Raheny Road will be diverted via Brookwood Avenue, Brookwood Rise, Harmonstown Road and Springdale Road.  
  • Pedestrian access will be maintained.
     

Richmond Road, Dublin 3.

$
0
0


A request has been received from The City Council’s, Road Maintenance Division for the temporary closure of the following road to facilitate road resurfacing work on the dates and times listed below:

Richmond Road (from Drumcondra Road Upper to Grace Park Road), Dublin 3.

Period 1:   From Monday 10th April 2017 to Wednesday 12th April 2017 between 19.30hrs to 06.00hrs per night.

Period 2:   From Monday 17th April 2017 to Wednesday 19th April 2017 between 19.30hrs to 06.00hrs per night.

Period 3:   From Monday 24th April 2017 to Wednesday 26th April 2017 between 19.30hrs to 06.00hrs per night.

Period 4:   From Tuesday 2nd May 2017 to Wednesday 3rd May 2017 between 19.30hrs to 06.00hrs per night.

Period 5:   From Monday 8th May 2017 to Wednesday 10th May 2017 between 19.30hrs to 06.00hrs per night.

Period 6:   From Monday 15th May 2017 to Wednesday 17th May 2017 between 19.30hrs to 06.00hrs per night.

Period 7:   From Monday 22nd May 2017 to Wednesday 24th May 2017 between 19.30hrs to 06.00hrs per night.
        
Traffic Management Plan

  • Traffic on Drumcondra Road wishing to travel on Richmond Road to Fairview Strand will be diverted via Griffith Avenue and Grace Park Road.
  • Pedestrian and local access will be maintained.

Ormond Road North, Dublin 9.

$
0
0

A request has been received from The City Council’s, Road Maintenance Division for the temporary closure of the following road to facilitate road resurfacing work on the dates and times listed below:

Ormond Road North (from Drumcondra Road Upper to Grace Park Road), Dublin 9.

Period 1:    From Monday 10th April 2017 to Wednesday 12th April 2017 between 19.30hrs to 06.00hrs per night.

Period 2:    From Monday 17th April 2017 to Wednesday 19th April 2017 between 19.30hrs to 06.00hrs per night.

Period 3:    From Monday 24th April 2017 to Wednesday 26th April 2017 between 19.30hrs to 06.00hrs per night.

Period 4:    From Tuesday 2nd May 2017 to Wednesday 3rd May 2017 between 19.30hrs to 06.00hrs per night.

Period 5:    From Monday 8th May 2017 to Wednesday 10th May 2017 between 19.30hrs to 06.00hrs per night.

Period 6:    From Monday 15th May 2017 to Wednesday 17th May 2017 between 19.30hrs to 06.00hrs per night.

Period 7:    From Monday 22nd May 2017 to Wednesday 24th May 2017 between 19.30hrs to 06.00hrs per night.

Traffic Management Plan

  • Traffic on Drumcondra Road Upper wishing to travel on Ormond Road to Grace Park Road will be diverted via Church Avenue.
  • Pedestrian and local access will be maintained at all times.
     

Botanic Avenue, Dublin 9.

$
0
0

A request has been received from The City Council’s, Road Maintenance Division for the temporary closure of the following road to facilitate road resurfacing work on the dates and times listed below:

Botanic Avenue (from Drumcondra Road Upper to Glendalough Road), Dublin 9.

  • Period 1:   From Monday 10th April 2017 to Wednesday 12th April 2017 between 19.30hrs to 06.00hrs per night.
  • Period 2: From Monday 17th April 2017 to Wednesday 19th April 2017 between 19.30hrs to 06.00hrs per night.
  • Period 3: From Monday 24th April 2017 to Wednesday 26th April 2017 between 19.30hrs to 06.00hrs per night.
  • Period 4: From Tuesday 2nd May 2017 to Wednesday 3rd May 2017 between 19.30hrs to 06.00hrs per night.
  • Period 5: From Monday 8th May 2017 to Wednesday 10th May 2017 between 19.30hrs to 06.00hrs per night.
  • Period 6: From Monday 15th May 2017 to Wednesday 17th May 2017 between 19.30hrs to 06.00hrs per night.
  • Period 7: From Monday 22nd May 2017 to Wednesday 24th May 2017 between 19.30hrs to 06.00hrs per night.

Traffic Management Plan

  • Traffic on Drumcondra Road Upper wishing to travel on Botanic Road will be diverted via Hollybank Road and Glendalough Road.
  • Traffic on Botanic Road wishing to travel on Drumcondra Road Upper will be diverted via Glendalough Road and Hollybank Road.
  • Pedestrian and local access will be maintained at all times.

Millmount Avenue and Millbourne Avenue, Dublin 9.

$
0
0

A request has been received from The City Council’s, Road Maintenance Division for the temporary closure of the following road to facilitate road resurfacing work on the dates and times listed below:

Millmount Avenue & Millbourne Avenue (from Drumcondra Road Upper to Ferguson Road), Dublin 9.

  • Period 1:      From Monday 10th April 2017 to Wednesday 12th April 2017 between 19.30hrs to 06.00hrs per night.
  • Period 2:    From Monday 17th April 2017 to Wednesday 19th April 2017 between 19.30hrs to 06.00hrs per night.
  • Period 3:    From Monday 24th April 2017 to Wednesday 26th April 2017 between 19.30hrs to 06.00hrs per night.
  • Period 4:    From Tuesday 2nd May 2017 to Wednesday 3rd May 2017 between 19.30hrs to 06.00hrs per night.
  • Period 5:    From Monday 8th May 2017 to Wednesday 10th May 2017 between 19.30hrs to 06.00hrs per night.
  • Period 6:    From Monday 15th May 2017 to Wednesday 17th May 2017 between 19.30hrs to 06.00hrs per night.
  • Period 7:    From Monday 22nd May 2017 to Wednesday 24th May 2017 between 19.30hrs to 06.00hrs per night.

Traffic Management Plan

  • Traffic on Drumcondra Road wishing to travel on Millmount Ave & Millbourne Ave to Ferguson Road will be diverted via Home Farm Road.
  • Pedestrian and local access will be maintained.
     

Easter Commemoration Events

$
0
0

A request has been received from Eamon O’Boyle & Associates on behalf the OPW for the temporary closure of the following roads to facilitate Easter Commemoration Events on the dates and times listed below:

  • Location A:    O’Connell Street
    Period:        from 05.00hrs to 15.00hrs on Sunday 16th April 2017.
  • Location B:    St. Stephen’s Green South
    Period:    from 20.00hrs on Saturday 15th April 2017 to 03.00hrs on Tuesday 18th April 2017.
  • Location C:    Custom House Quay (from Butt Bridge to Talbot Memorial Bridge)
    Period:        from 07.00hrs on Sunday 16th April 2017 to 24.00hrs on Monday 17th April 2017.
  • Locations D:    Haymarket
    Period:        from 08.00hrs on Sunday 16th April 2017 to 24.00hrs on Monday 17th April 2017.
  • Location E:    Smithfield, New Church Street, Arran Quay Terrace and Burgess Lane
    Period:        from 08.00hrs to 24.00hrs on Monday 17th April 2017.

Traffic Management Plan

  • Southbound Buses and taxis on Parnell Square East & Cavendish Row wishing to travel on O’ Connell Street to D’Olier Street will be diverted via Parnell Street, Cumberland Street, Marlborough St, Rosie Hackett Bridge and Burgh Quay.
  • Traffic on Leeson Street Lower wishing to travel on St Stephens Green South to Cuffe Street & St. Stephens Green West will be diverted via Earlsfort Terrace, Hatch Street Upper and Harcourt Street.
  • Northbound traffic on O’Connell Bridge wishing to access Parnell Street will be diverted via Eden Quay, Beresford Place and Gardiner Street Lower.
  • Traffic from Eden Quay / Butt Bridge wishing to travel on Custom House Quay will be diverted via Beresford Place and Memorial Road
  • Pedestrian and local access will be maintained

Railway Street, Dublin 1.

$
0
0

A request has been received from The City Council’s, Road Maintenance Division for the temporary closure of the following road to facilitate road reconstruction work on the dates and times listed below:

  • Railway Street, Dublin 1 from 00.00hrs on Monday 17th April 2017 to 24.00hrs on Friday 28th April 2017.

Traffic Management Plan

  • Pedestrian and local access will be maintained.

Spire View, Dublin 7.

$
0
0

A request has been received from The City Council’s, Road Maintenance Division for the temporary closure of the following road to facilitate road reconstruction work on the dates and times listed below:

  • Spire View (from Phibsborough Avenue to the end of cul de sac), Dublin 7 from 00.00hrs on Tuesday 2nd May 2017 to 24.00hrs on Sunday 7th May 2017.

Traffic Management Plan

  • Pedestrian and local access will be maintained.
     

Findlater Place, Dublin 1.

$
0
0


A request has been received from The City Council’s, Road Maintenance Division for the temporary closure of the following road to facilitate road reconstruction work on the dates and times listed below:

  • Findlater Place, Dublin 1 from 00.00hrs on Monday 24th April 2017 to 24.00hrs on Sunday 30th April 2017.        

Traffic Management Plan

  • Pedestrian and local access will be maintained.

Beaver Street, Dublin 1.

$
0
0

A request has been received from The City Council’s, Road Maintenance Division for the temporary closure of the following road to facilitate carriageway resurfacing on the dates and times listed below:

  • Beaver Street (from Foley Street to Railway Street), Dublin 1 from 00.00hrs on Monday 17th April 2017 to 24.00hrs on Friday 28th  April 2017.

Traffic Management Plan

  • Pedestrian and local access will be maintained.

Fishamble Street, Dublin 8.

$
0
0

The City Council’s Road Maintenance Division intends to close the following road to facilitate the Handel’s Messiah event on the date and times listed below:

  • Fishamble Street (from Lord Edward Street to Essex Street West), Dublin 8 from 07.00hrs to 17.00hrs on Thursday 13th April 2017.

Traffic Management Plan

  • Traffic on Wood Quay wishing to travel on Fishamble Street to Lord Edward Street, will be diverted via Exchange Street Lower and Parliament Street.
  • Traffic on Lord Edward Street wishing to travel on Fishamble Street to Exchange Street Lower and Wood Quay will be diverted via Exchange Street Upper, Essex Gate, Essex Street East, Eustace Street and the South Quays.
  • Pedestrian access will be maintained.

Virgin Media Night Run 2017

$
0
0

Athletics Ireland intends to close the following roads to facilitate the Virgin Media Night Run 2017 on the date and times listed below:

A request has been received from Athletics Ireland for the temporary closure of the following roads to facilitate the Virgin Media Night Run 2017 on the dates and times listed below:

  • Location 1: North Wall Quay (from Samuel Beckett Bridge to Castleforbes Street), Dublin 1 from 18.30hrs to 21.30hrs on Sunday 23rd April 2017.
  •  
  • Location 2: North Wall Quay (from Commons Street to Samuel Beckett Bridge), Dublin 1 from 19.00hrs to 23.15hrs on Sunday 23rd April 2017.


In addition to temporary road closures there will be temporary traffic lane closures on the race route from North Wall Quay (NWQ), Custom House Quay (CHQ), Eden Quay (EQ), O’Connell Street, Cathal Brugha Street, Marlborough Street, EQ, CHQ, Talbot Memorial Bridge, City Quay, Sir John Rogerson’s Quay (SJRQ), Benson Street, Hanover Quay, Misery Hill, Macken Street, Pearse Street, Ringsend Road, Bridge Street, Irishtown Road, Seapoint Terrace, Pembroke Street, Sean Moore Road, East Link Bridge and North Wall Quay between 21.00 and 23.00hrs


Traffic Management Plan

  • Traffic on Bachelors Walk wishing to travel on Eden Quay, Custom House Quay & North Wall Quay to East Link Bridge will be diverted via O’Connell Street, Parnell Street, Parnell Square, Granby Row, Dorset Street, North Circular Road, Portland Row, North Strand Road, Annesley Place, Poplar Row and East Wall Road.
  • Traffic on East Wall Road wishing to travel on North Wall Quay to Burgh Quay will be diverted via East Link, Sean Moore Road, Bath Street, Irishtown Road, Bridge Street, Ringsend Road, Pearse Street and Tara Street.
  • Pedestrian and local access will be maintained.
  • Traffic on Memorial Road wishing to travel on City Quay /Lombard Street to Westland Row/ Pearse Street will be diverted via Moss Street and Townsend Street.
  • Traffic on Pearse Street wishing to travel on Macken Street/Cardiff Lane/ Samuel Beckett Bridge to North Strand Road will be diverted via Tara Street, Butt Bridge, Beresford Place and Amiens Street
  • Pedestrian and local access will be maintained.
     
Viewing all 755 articles
Browse latest View live




Latest Images